Watergram-Behrampora Road
Watergram-Behrampora Hib Dangerpora Road
20.13 Km Road completed and handed over to R&B Deptt

Loan:

2151-IND
Category: Engineers Design
Location: Kashmir Transport Roads
Districts Passing: Baramulla

Constituency Passing:

Rafia-abad
Status: Works Completed
ERA Ref: Transport/Srinagar/Road 11 Type:Works Mode: NCB
ERA Pac ID: 0010
PCSS No: 0048
Scope of Work: 20.13 Km
Contract Cost in Rs crore: 13.95
Dynamic Cost in Rs crore: 15.28
Contractor Details Dinesh Chander R Agarwal
Date of Signing of Contract 30 July 2007
Date of Start of Work (NTP) 24 August 2007
Completion Period (18 Months)
Completion Date as per Contract 21 February 2009
 
Retaining Wall :- 6880 m completed out of 6880 m
Breast wall :- 620 m completed out of 620 m
Drain length :- 2870 m completed out of 2870 m
Pipe Culvert :-27 Nos Completed out of 27 no
Box Culvert :- 7 Nos Completed out of 7 no